Nineteenth-Century Infrastructure Delivery Record From Kilmore Quay
Through iProperty Radio, Place Engage is undertaking a non-political placemaking series across 26 counties throughout the 26 weeks of Ireland’s EU Council Presidency. Each county week builds a Placemaking Data Baseline from primary sources before arrival, then tests that baseline against what people on the ground actually say.
This week, Week 4, our listening tour brought us to County Wexford, and you can catch up in full at: https://placeengage.com/week-4-wexford-one-county-several-markets-happy-residents-in-a-heatwave/
I grew up hearing about the significance of Hook Head (https://tidesandtales.ie/by-hook-or-by-crooke/) and have maintained a lifelong fascination with lighthouses ever since. One of my post-Covid highlights was staying in the lighthouse on Clare Island, off the Mayo coast, and I’m on a mission to visit and/or stay in all of the Great Lighthouses of Ireland!
And this lead to some research in advance of our arrival that influenced our perspective, particularly Rita Edwards’ chapter of on ‘Kilmore Quay, County Wexford, 1800–1900’, in Karina Holton, Liam Clare and Brian Ó Dálaigh (eds), ‘Irish Villages: Studies in Local History’ book.
Most Irish villages can be explained by something already there – a chapel, a crossroads, a bridge, a landlord’s plan. Edwards makes the case that Kilmore Quay [Crossfarnogue and Nemestown] cannot. There was no village on the coast at the start of the nineteenth century and no plan for one. What existed was a small pier at Crossfarnogue, in the shelter of Forlorn Point, put up by local fishermen with their friends and neighbours in 1795. The settlement grew around it.
That reverses the usual sequence, and it is why the chapter reads, for a built-environment audience, less like local history and more like a long-form project history. The account of the pier really is the account of the village.
A capital project that took fifty-six years to deliver
The chronology Edwards presents from OPW files is unusually complete:
- 1795: Small pier built by local fishermen, their friends and neighbours, in the shelter of Forlorn Point
- 1836: An inquiry estimates that £3,000 would materially improve conditions. Nothing is done. The reason recorded is the absence of local quarries.
- August 1843: With no state funding forthcoming, the fishermen resolved to build it themselves. The boat masters raise £224 in cash, with contributions from Wexford town and Waterford city. Free labour is valued at £38. Local farmers provide the free use of 310 horses, their labour reckoned at 2s 6d each. A memorial to the OPW in December 1844 lists the masters and their boats.
- Winter 1843/4: A large vessel loses its moorings, carries away part of the newly worked pier, and is left wrecked across the entrance.
- Spring 1844 onwards: Local fishermen learn of a £50,000 government fishery fund offering to treble locally raised money.
- December 1844: A committee forms with Andrew Furlong of Newtown as secretary; a memorial goes forward signed by 89 locals, nearly all fishermen, and 18 of the local gentry. The supporting economic case is made – 77 boats and 176 men fishing the parish, more than a thousand dependants, collective annual income between £1,000 and £1,500, and an argument that better shelter would allow bigger boats, access to the Nymph Bank, and a threefold increase in earnings.
- 1845: The board’s engineer William Fraser draws up a £2,000 scheme. Certified accounts are returned to the commissioners every two to four weeks; one, dated 21 October 1845, covers 614 men and 50 horses over three weeks for £37 15s 11d. A second engineer, Barry Gibbons, raises reservations about the suitability of the material being used. The fishermen had always built with what was to hand – stone taken from the western side of the pier itself and from Forlorn Point – which is recognised as exposing the wall to Atlantic storms and to silting from Ballyteigue Burrow. An inland quarry is opened. Storms carry away part of the works twice over the winter.
- By December 1845 the pier was declared unsafe.
- 1846: The committee has £18 in hand. A second memorial in April is signed by twenty fishermen. An autumn appeal raises £70 and draws £210 in response, with notice that the piers and harbours fund is exhausted. The Board advises them simply to finish what exists in a round and sloping form. Seven days after that work was completed, on 20 November 1846, a gale drove a 500-ton copper ship into the pier while it shelters, opening a breach 60 feet long, 54 feet wide and 9 feet deep and destroying upwards of ten feet of parapet. Gibbons’s report concludes that the fishermen had laboured “under an extraordinary misconception” in assuming that rude construction and local material would serve for a seaward extension.
- By 31 December 1846, over £1,000 had been spent and the work was unfinished.
- 1847/48: James Farrell, admiralty engineer and county surveyor for Wexford, revisits the site with Gibbons and prepares new plans. In July 1848 the Admiralty, Harbour and Railway Department in London cleared the project. Construction and approach road are estimated at £6,000: £4,000 by grant, £2,000 by loan, with the grand jury striking a cess on the inhabitants of every townland in the parish of Kilmore to repay it.
- 1849–51: Work begins on 24 March 1849 under a stonemason, Patrick Maher. This time the stone is sourced outside the locality. Machinery is bought in Wexford and moved to Fethard-on-Sea, where suitable stone is quarried and then shipped round to Crossfarnogue by boat, the boats running day and night whenever weather allows. Two years later the parish had a stone pier of nearly 800 feet reaching into seven feet of water at low-water springs.
For context, my spatial planning interest is in informed public participation, and in order to move in this direction, there needs to be genuine and tactical capacity building across communities to ensure the resilience that the local fishermen of Kilmore Quay showed back in the 1840s and 1850s. This is true of all communities, but arguably double for rural and coastal communities.
The pattern above will be familiar to anyone who has worked on modern day marine or coastal schemes with a sound local demand case, but an under-scoped first estimate, community/volunteer/stakeholder equity in the form of unpriced labour, a specification failure identified by an engineer and overruled by cost, repeated storm loss, and eventual delivery only once the material specification was corrected and the funding structure was put on a proper grant-and-loan footing with a repayment mechanism attached.
Delivery did not end the exposure. The chapter tracks a further cycle: £6,375 by grant from the Irish Church Fund in the mid-1880s with a further £2,125 by loan; the October 1896 storm, reported in the Wexford Independent as the worst in twenty-five years, which washed away the centre of the pier and storm wall, scattered nearly 200 tons of stone and damaged the concrete breakwater; and an August 1901 examination that declared the pier unfit for the purpose for which it was built.
Following the Local Government (Ireland) Act 1898, responsibility for the pier and harbour passed to Wexford County Council, and in April 1902 the Council agreed to fund £500 towards repairs with a matching £500 from the Department of Agriculture. A locally built asset became, over roughly a century, a local authority asset with a departmental funding partner. The 1955 fishermen’s co-operative, European Regional Development Fund support, and the £3.5 million harbour opened in May 1997 continue the same line.
Edwards sets two population tables side by side, showing that between 1841 and 1911 the inland cluster of Kilmore Upper, Sarshill and Ballask fell from 538 to 191. Over the same period the coastal townlands of Crossfarnogue and Nemestown, which became Kilmore Quay, rose from 249 in 1841 to a peak of 497 in 1861 before settling at 293 in 1911. County Wexford’s population fell by 11% across the Famine decade; the parish of Kilmore rose by 7%, from 4,761 to 5,071.
That does not align with the experiences of coastal communities on the West coast of Ireland during that period, and it appears to be less attributable to population growth, and more about population redistribution within a parish, toward work, food and shelter – the harbour works, the Ballyteigue drainage scheme, and access to fish, wildfowl and the shore. It is also a reminder for anyone assembling a county baseline that settlement-level movement can run in the opposite direction to the county aggregate, and that the aggregate will conceal it (a bit like how the ‘average’ man with his head in the oven and his feet in the freezer is, on average, fine – averages hide the reality).
The housing quality data from the 1901 census is equally direct. Of 25 houses returned at Kilmore Quay, seven – 28% – were substantially built of durable materials, two of them public houses. The remaining eighteen were mud-walled and thatched. The outbuildings returned alongside them, ten stables and six pig houses among them, show a coastal village still substantially dependent on land.
What I took from this account:
- Infrastructure can precede and produce settlement
- Whole-life material specification is a placemaking decision – the 1840s pier failed on materials, twice, and the failure was identified in advance and set aside on cost. The 1849 pier succeeded because stone was brought from Fethard-on-Sea at greater expense. Fifty-six years separate the first estimate from the working pier.
- Social capital and community delivery today are incredibly difficult to value, so it was interesting to see this recorded on a 1840s balance sheet (310 horses, the £38 of free labour, the 614 men on a three-week account).
*I am not a place historian and do not fully understand how to map the historical impacts into the place experienced by residents today — so I may have drawn unfair or inaccurate parallels — corrections and additions welcome and encouraged: carol@placeengage.com